Matunuck Beach Road Stabilization


Sheet Pile / Cofferdam

47' Sheet pile installed for the main road protection down to tip elevation of -32 MLW.  Temporary sheet pile coffer dam installed to set stone

11 Ton Rip Rap

11 Ton stone set inside of cofferdam down to elevation -8.0 MLW

Concrete wall and Cap

Galvanized reinforcing rod installed for 30" concrete cap

 

Project Goals

Matunuck Beach Road Stabilization is a project design to provide protection for Matunuck Beach Road and the residence from the Atlantic Ocean which has been eroding the beach over the last 50 years. The goal is to provide a seaward protection of the road so that residence and emergency services have access to the area.